UP Berteau Avenue Bridge (North Center)


Click the photo to view the full-size version

1/7
Date Taken:
Author:
Caption:

Name UP Berteau Avenue Bridge (North Center)
Chicago & North Western Railway Bridge #1304 1/4
Built By Chicago & North Western Railway
Currently Owned By Union Pacific Railroad
Superstructure Contractor Lassig Bridge & Iron Works of Chicago
Substructure Contractor Unknown
Length 70 Feet Total
Width 3 Tracks, 2 In Use
Height Above Ground 11 Feet 10 Inches
Superstructure Design Through Plate Girder
Substructure Design Stone Masonry
Date Built 1897
Date Replaced 2020
Traffic Count 0 Trains/Day (Bridge has been Replaced)
Current Status Replaced by a new bridge
Chicago & North Western Railway Bridge Number 1304 1/4
Union Pacific Railroad Bridge Number 5.72
Significance Local Significance
Documentation Date 7/30/2015

In the early 1850s, several railroad companies began constructing railroad lines radiating from Chicago.  In 1855, the Chicago & Milwaukee Railroad (C&M) constructed a 45-mile railroad line, extending north from an existing railroad line at Ashland Avenue and Armitage Avenue in Chicago to the Wisconsin State Line near Kenosha.  At the same time, the Milwaukee & Chicago Railroad (M&C) constructed an additional 40 miles north to Milwaukee.  The two railroads would be consolidated into a new railroad known as the Chicago & Milwaukee Railroad (C&M) soon after completion, and would come under control of the Chicago & North Western Railway (C&NW) in 1866.  The C&M was leased to the Chicago, Milwaukee and North Western Railway (CM&NW) in 1883.  The C&NW acquired control of the CM&NW soon after.   The C&NW had constructed and acquired a large network of railroad lines through the Midwest.  This line formed a portion of the principal north mainline of the C&NW, eventually extending to northern Wisconsin and the Upper Peninsula of Michigan.  Due to increasing traffic along this line, a second track would be constructed between 1890 and 1892.

In the late 19th Century, railroad traffic had become a significant safety hazard for the City of Chicago.  A solution was devised to elevate the railroad tracks throughout the city, placing the railroads upon embankments and constructing subways at each street.  In 1898, the C&NW completed track elevation and a third track from Ashland Avenue to Balmoral Avenue; followed by Balmoral Avenue into Evanston between 1907 and 1910.  The C&NW would become a prominent railroad in the Midwest, eventually building a system over 11,000 miles long.  Throughout the 20th Century, this line would continue to be an integral part of the C&NW system.  The second track would be removed north of Kenosha after 1959.  In 1995, the C&NW would be purchased by the Union Pacific Railroad.  Union Pacific continues to operate the route as the Kenosha Subdivision.  Metra operates a commuter service, the Union Pacific-North Line over the Chicago to Kenosha section.


View an article discussing this track elevation project (digitalized by Google)

This bridge once carried the Union Pacific North Line over Berteau Avenue near Ravenswood Avenue in the North Center neighborhood of Chicago. During the late 19th Century, railroad traffic within the City of Chicago posed a serious hazard to the general population. Starting in the mid-1890s, the City of Chicago passed a number of ordinances mandating the elevation of tracks within the city. An ordinance was passed on March 30th, 1896 requiring the elevation of the Milwaukee Division of the Chicago & North Western Railway (C&NW) between Diversey Parkway and Balmoral Avenue. Construction began soon after, and was largely completed in 1897. This section of track elevation required relatively few retaining walls, and the fill was constructed of sand shipped from Indiana. This project was one of the first large scale track elevation projects in Chicago.

This bridge was constructed in 1897 as part of the track elevation project between Diversey Parkway and Balmoral Avenue. The bridge consisted of a 70-foot through plate girder span, set onto stone abutments. The girder spans were typical for early track elevation projects, consisting of a traditional floor constructed of stringers and floorbeams, covered by a sheet metal deck. In addition, the ends of the girders were rounded. The bridge was initially constructed for three tracks, although the westernmost track had been removed in the 1980s. Lassig Bridge & Iron Works fabricated the girders for this track elevation project. This company fabricated numerous spans for the C&NW, and had its shop along this line at Wrightwood Avenue. However, the industrial lead into the Lassig shops was too sharp to allow the spans for this project to be shipped whole, and the pieces were instead assembled at the division shops before being installed. Stone for the abutments was quarried at a railroad owned quarry near Duck Creek, Wisconsin, and the abutments and retaining walls were constructed by contract.

This type of structure was initially popular for grade separations in Chicago, but fell out of favor as trough floor spans and concrete spans became more economical. The metal floor of this design of bridge was susceptible to pooling water, which would cause corrosion to the steel. In addition, the through girder design limited horizontal clearances on the bridge. By the early 2010s, Metra sought to replace 11 bridges between Balmoral Avenue and Grace Street. The bridge was replaced in stages, and the west track was initially removed in 2011 to allow for construction of the new west track. Once the west track was completed in 2017, the center track was replaced between 2018 and 2019. After the center track was completed, the eastern track was removed. The replacement bridge consists of a double track through plate girder span, set onto new concrete abutments. The eastern portion of the stone abutment was capped with concrete, and remains unused. Overall, the bridge was in poor condition at the time of replacement, with significant section loss and deterioration seen throughout the superstructure. The author has ranked this bridge as being locally significant, due to the common design.


Citations

Builder and build dates Railroad Gazette; Volume 28
Railroad History Citation ICC Valuation Information, Compiled by Richard S. Steele