UP Montrose Avenue Bridge (Irving Park)


Click the photo to view the full-size version

1/14
Date Taken:
Author:
Caption:

Name UP Montrose Avenue Bridge (Irving Park)
Chicago & North Western Railway Bridge #W8 1/4
Built By Chicago & North Western Railway
Currently Owned By Union Pacific Railroad
Design Engineer William H. Finley
Length 136 Feet Total, 40 Foot Main Spans
Width 6 Tracks, 4 In Use
Height Above Ground 13 Feet 8 Inches
Superstructure Design Concrete Encased Beam and Concrete Slab
Substructure Design Concrete
Date Built 1917
Traffic Count 75 Trains/Day (Estimated)
Current Status In Use
Chicago & North Western Railway Bridge Number W8 1/4
Union Pacific Railroad Bridge Number 7.50
Significance Local Significance
Documentation Date 7/7/2018

In the early 1850s, several railroad companies began constructing railroad lines radiating from Chicago. The Illinois & Wisconsin Rail Road Company constructed 39 miles of new railroad, extending from Chicago to Cary, Illinois.  The following year, the railroad would be controlled by William B. Ogden, and consolidated into the Chicago, St. Paul & Fond du Lac Rail Road (CStP&FDL).  The CStP&FDL constructed an additional 53 miles to Janesville, Wisconsin in 1855.  The CStP&FDL would be purchased by the Chicago & North Western Railway (C&NW) in 1859.  The C&NW was beginning to construct and acquire a large network of railroads throughout the Midwest.  This line formed a portion of the principal northwest mainline of the C&NW, eventually extending to St. Paul, Minnesota.  At Janesville, traffic was required to run south to Afton to reach the line to Janesville.  Due to increasing traffic along this line, a second track would be constructed beginning in 1882, when a second track was completed from Chicago to Mayfair (Montrose Avenue).  By 1884, the route was double tracked to Des Plaines. 

In 1886, the Janesville & Evanston Railway was incorporated by the C&NW to construct 16 miles of new railroad, connecting Janesville with the existing line at Evansville, Wisconsin.  The railroad would be purchased by the C&NW the following year. By 1893, further double tracking was constructed to Barrington, followed by from Barrington to Janesville between 1898 and 1899.  In the late 19th Century, railroad traffic had become a significant safety hazard for the City of Chicago.  A solution was devised to elevate the railroad tracks throughout the city, placing the railroads upon embankments and constructing subways at each street.  In 1899, the C&NW completed a track elevation from Sangamon Street to Kostner Avenue; followed by Kostner Avenue to Foster Avenue in 1918.  During each of these elevation programs, a third track would be constructed. A third track was completed to Barrington in 1930.  The C&NW would become a prominent railroad in the Midwest, eventually building a system over 11,000 miles long.  Throughout the 20th Century, this line would continue to be an integral part of the C&NW system.  The second track would be removed between Janesville and Harvard in the 1950s.  In 1995, the C&NW would be purchased by the Union Pacific Railroad.  Union Pacific continues to operate the route as the Harvard Subdivision.  Metra operates a commuter service, the Union Pacific-Northwest Line over the Chicago to Harvard section.


View an article describing the design of this bridge

Located in the Irving Park neighborhood of Chicago, this concrete encased beam bridge carries the Metra Union Pacific Northwest Line over Montrose Avenue. In the late 19th Century, the numerous grade crossings throughout the city represented a hazard to the general public. In response, the City of Chicago passed numerous ordinances, requiring the elevation of freight railroads within city limits. By the 1910s, many of the major railroads within the city had been elevated. At street crossings, subways were constructed to carry railroads over the roadway. An ordinance was passed on December 29, 1913, requiring the elevation of the Chicago & North Western Railway line between a previous track elevation project at Kostner Avenue and Foster Avenue. With the requirements, the city allowed for a lenient completion date of July 1st, 1927. Work did not begin until 1916, with the majority of the construction completed in 1917. The entire project was finished by early 1918. Typical of 20th Century track elevations, the line was constructed with concrete retaining walls, and was generally constructed for three tracks.

The bridge at Montrose Avenue uses a typical design for this track elevation project, with two concrete encased beam spans, approached by a slab span on either end. The main spans of the bridge are 40 feet in length, while the approach spans of the bridge are 28 feet in length. The entire bridge is set onto concrete substructures, and the bridge runs at a heavy skew. The piers of the bridge utilize a typical design for the era, utilizing concrete columns connected by arches. This particular design was standard for most railroads throughout the United States, and provided a decorative aesthetic to bridges in urban areas. Designed by C&NW bridge engineer William H. Finley, the main spans of the bridge use concrete encased beam spans, which were constructed offsite. These spans concentrate the loading in the internal steel beams, while the main function of the concrete is to protect the steel structure. The approach spans are constructed monlithically with the abutments, which was an innovative design at the time of construction. Concrete walkways are cantilevered from both faces of the bridge, and the structure was originally constructed for six tracks. Overall, the bridge appears to remain in fair condition, with some minor deterioration noted on the substructures. However, the superstructure appears to be in better condition than similar bridges of a similar age, with very little deterioration noted. Today, the bridge continues to carry four tracks. The author has ranked the bridge as being locally significant, due to the common design.


Citations

Build date Engineering News-Record; Volume 80, Issue 11
Railroad History Citation ICC Valuation Information, Compiled by Richard S. Steele

Loading...