Name UP Bridge #160.28
Chicago & North Western Railway Bridge #485
Built By Chicago & North Western Railway
Currently Owned By Union Pacific Railroad
Superstructure Contractor Unknown
Substructure Contractor Widell Company of Mankato, Minnesota
Unknown (Concrete Alterations)
Length 60 Feet Total
Width 2 Tracks
Height Above Ground 10 Feet (Estimated)
Superstructure Design Through Plate Girder
Substructure Design Stone Masonry
Date Built 1901
Traffic Count 50 Trains/Day (Estimated)
Current Status In Use
Chicago & North Western Railway Bridge Number 485
Union Pacific Railroad Bridge Number 160.28
Significance Local Significance
Documentation Date 4/23/2018

In 1856, the Chicago, Iowa & Nebraska Rail Road (CI&N) began construction on a new mainline across Iowa, connecting an existing Galena & Chicago Union Railroad (G&CU) line at Fulton, Illinois to the Missouri River.  To establish construction, a temporary ferry was installed across the Mississippi River at Clinton in 1856.  In 1857, the first 44 miles were completed to Wheatland, Iowa.  The following year, 20 miles were completed to Lisbon, Iowa; and in 1859, an addition 17 miles were completed to Cedar Rapids, Iowa.  In 1861, the Cedar Rapids & Missouri River Railroad (CR&MR) constructed an additional 41 miles to Chelsea, Iowa; followed by 29 miles to Marshalltown, Iowa in 1862.  After pausing in 1863, an additional 29 miles were completed to Nevada, Iowa in 1864, followed by 23 additional miles to Boone, Iowa in 1865. In 1864, both the CI&N and CR&MR were leased by the Chicago & North Western Railway (C&NW). In 1867, the line continued west from Boone, reaching the Missouri River at Council Bluffs, Iowa in 1867.

During the second half of the 19th Century, the C&NW had constructed and acquired a large amount of trackage throughout the Midwest.  This line formed a principal mainline for the C&NW, connecting western railroads at Omaha to the railroad hub of Chicago.  In  1884, the C&IN and CM&MR were formally acquired by the C&NW.  In 1887, the Linn County Railway (LC) constructed a 6-mile cutoff, bypassing Cedar Rapids to the south between Otis, Iowa and Beverly, Iowa.  At the end of the year, the LC was formally acquired by the C&NW.  During the late 19th Century, several other improvements were made to this line.  Between 1890 and 1891, a second track was constructed between Clinton and Lowden, Iowa; and between Libson and the Cedar River bridge.  Between 1893 and 1894, a second track was constructed between Lowden and Lisbon.  A second track was added to the original mainline through Cedar Rapids in 1898, and between 1898 and 1899, a second track was constructed between the Cedar River bridge and the west side of Marshalltown.  In 1901, a second track was completed between Marshalltown and Boone, and new facilities were constructed at Boone. Throughout the 20th Century, the Cedar River bridge remained a gauntlet structure, severely hindering efficient operations.

By the 20th Century, the C&NW was operating an extensive railroad network, which radiated north and west from Chicago.  This line served as the backbone of the C&NW, connecting transcontinental freight and passengers at Omaha to Chicago.  Known as the Overland Route, this line became one of the most significant railroad routes in the United States.  This route saw continuous upgrades during the 20th Century, including significant bridge, rail, tie and signal upgrades.  In 1995, the C&NW was purchased by Union Pacific Railroad (UP).  In 2002, UP constructed a second track at the Cedar River bridge, eliminating a single track bottleneck in the network.  Today, this line remains vital to UP and is still well maintained.  The Clinton to Boone segment is known as the Clinton Subdivision, and remains a heavily used double track mainline.


Located between Lamoille and State Center, this through plate girder bridge carries a former Chicago & North Western Railway mainline over an unnamed creek near 220th Street. The first bridge at this location was likely a timber pile trestle bridge, constructed when the line was first built. It is unclear if the bridge was constructed with an iron bridge prior to the 20th Century. Between 1898 and 1902, the C&NW undertook a large double tracking project between Cedar Rapids, Iowa and Council Bluffs, Iowa. As part of the project, a new double track bridge was constructed here in 1901. Currently, the bridge consists of a single 60-foot through plate girder span, set onto stone and concrete substructures. The superstructure follows a standard design, with two heavy plate girders, a standard floor and square girder ends. The substructure also follows a standard design, with abutments that have been rebuilt with new backwalls. Stone for the substructures consists of a yellow limestone, quarried at Mankato, Minnesota. An unknown contractor fabricated the superstructure, while it is believed that the Widell Company constructed the substructure. It is unclear if the alterations to the abutments were completed by railroad company forces or by an unknown contractor. The Widell Company constructed many of the stone bridges and culverts along the Iowa Division between the late 1890s and approximately 1903. Through plate girder spans were popular for railroad use, as they were durable and easy to construct. Since the initial construction, the bridge has seen a number of alterations, including concrete repairs to the abutments in 1929 and 1955 and strengthening of the superstructure in 1922, 1933, 1941 and 1951. Today, the bridge remains in use as part of a Union Pacific Railroad mainline. Overall, the bridge appears to be in fair to good condition, with no significant deterioration noted. The author has ranked the bridge as being locally significant, due to the common design.


Citations

Build date Chicago & North Western Railway Valuation Notes at the Chicago & North Western Historical Society Archives
Builder (substructure) The Improvement Bulletin; March 31, 1900
Railroad History Citation ICC Valuation Information, Compiled by Richard S. Steele